Minnesota Department of Transportation

511 Travel Info

Hwy 212 & Hwy 22

Glencoe Transportation Study

Promise to the public

MnDOT, the City of Glencoe and McLeod County promised to work with the greater Glencoe community to ensure that the community's concerns and aspirations were directly reflected in the alternatives developed as part of the transportation study and to provide feedback on how the community influenced recommendations and decisions.

Opportunities for public participation

Event type Date held # of attendees/respondents
Stakeholder workshop December 2018 45
On-line survey February 2019 213
Open house/community carnival February 2019 145
Stakeholder workshop May 2019 47
On-line & paper survey May 2019 805
Open house September 2019 110

What we heard

The public identified key issues for both Hwy 212 and the route that Hwy 22 takes through Glencoe. The public also gave their input on which potential improvements they could support on Hwy 212 as well as potential Hwy 22 re-routes.

Feedback on Hwy 212

The public identified four key issues for Hwy 212:

  1. There is confusion at intersections
  2. There is a need for walking and biking improvements
  3. Concern around speed limits
  4. There is a need to plan for increased traffic and future growth

All proposed safety improvements, single lane roundabouts and J-turns received support from the community.

Feedback on Hwy 22 re-route

The public identified four key issues for Hwy 22:

  1. There is confusion about the current route of Hwy 22
  2. Trucks have issues making turns
  3. There is a desire to remove heavy truck traffic from the downtown
  4. There is a need for walking and biking improvements
  5. Concern around speed limits
  6. There is a need for better signage

All four potential re-routes of Hwy 22 received support (image below). Keeping the current route of Hwy 22 was not widely support.

remaining routes